PMP模拟题精选15

qustions 1:
1. in a matrix organization, which of the following is not a responsibility of the project
manager?

complete task definitions
resource requirement definitions
major timetable milestones
personnel perfonmnce measurements


qustions 3:

the state of being totally answerable for the satisfactory completion of a specific assignment is called:


authority
accountability
responsibility
fiduciary

qustions 5:

you are responsible for the communication controls for the genesis series of satellites. your current assignment is:


project management
functional management
facility management
program management

qustions 2:
of the following, which usually exhibits the slowest rate of change?

people
technology
organizations
the environment

qustions 4:

during the planning phase of your current project, you prepare a detailed
financial plan. for this process, you are using:


a general imnagement skill
an industry specific skill
a skill that is common to general management and project management
a project management skill

qustions 6:

which of the following knowledge areas are part of project closure?

communications
scope
cost
human resources